Business case for a Feedermax containership with a shore power battery

A 12.5 MWh battery costing €2M can save ~ €50,000 per year for a 1,730 TEU containership

Shore power for containerships is mandatory from 2030 onwards as per FuelEU. The creation of shore power infrastructure remains difficult and takes a long time however. Mobile shore power solutions, with- or without a battery will ensure port authorities compliance to regulations. 

This case study determines the business case of a mobile shore power battery (a ‘power barge’) for a 1,730 TEU containership (the CMA CGM Feedermax) in the Port of Rotterdam. It is assumed the average power demand is 329 kW, the maximum power rating is 1 MW, resulting in an LVSC system with two 20-ft container batteries tailor-made for this ship type. Multiple scenarios are considered and a sensitivity analysis is made for both ship and power barge. Key factors are average power demand and time at berth, which combined result in the battery size and impacts most of the CAPEX and OPEX parameters.

The annual costs savings for the ship with an electricity price of 0.40 EUR per kWh and 40 shore power days per year are in the order of €50k. Most cost reductions are due to reduced compliance cost: it is estimated more than €600,000 can be saved with FuelEU alone in the first 10 years. Conservative estimates for maintenance and EU ETS pricing are considered, which could result in a more positive case. Total CAPEX costs for refit of the ship are estimated at €900,000. Payback time with these CAPEX and savings are still well beyond 10 years, resulting in a non-viable business case when considered purely economically. Improvements to the business case can include reduction of CAPEX, reduced kWh price or a differing set of assumptions. 

Use the tool below to customize a case study for yourself. 


Ship - Technical

The technical goal for the shore power refit of the CMA CGM Feedermax is to provide all power while moored electrically, thereby eliminating the need for using the vessel's onboard generators, reducing emissions and fuel consumption. As such, the vessel will need to be able to receive the power onto its main switchboard at the right specifications before it can turn off its engines. 

Average power demand for this ship type is determined using the Average Shore Power Demand tool. For this particular case study it is assumed one auxiliary engine operates at 30% load, resulting in an average power demand of 329 kW and energy demand of 8,482 kWh per day.

For the container ship setup, it is assumed that the shore power infrastructure is not available. This leads to the most conservative estimate in terms of technical and economic requirements, but can be considered somewhat ‘unfair’ as containerships need to be able to accomodate shore power by 2030 as per FuelEU requirements. Nonetheless for this instance the refit assumes necessary equipment modifications to be required and a connection system to integrate shore power is to be installed. The following breakdown covers the components required for connecting the ship to shore power and the key technical considerations.


Ship - Economical

For this case study it is assumed the shore power equipment needs to pay itself back by means of either fuel cost reduction, maintenance cost reduction, compliance cost reduction or a combination of all. This is not entirely fair, considering shore power will be made mandatory by 2030, which does not necessitate the requirement for a business case as it would simply be a necessity. Nonetheless, both a CAPEX and OPEX estimation were made, which resulted in a business case as shown below.


Power Barge - Technical

The power barge serves as both a mobile shore power solution and an energy hub, designed to provide shore power to ships via batteries if needed. The system is structured around separate charging (incoming power) and discharging (outgoing power) systems, ensuring efficiency, reliability, and scalability. In other words, this provides modular conversion systems for both AC and DC power handling, which can be changed or swapped more easily if needed. This applies to the battery containers too, which are assumed to be CATL Tener-X battery packs. Furthermore it is assumed only containerships will be serviced, reducing the technical complexity as no dedicated cable management system is needed. Below is a detailed breakdown of the main components and their key parameters.


Power Barge - Economical

With current assumptions on the base case (66% uptime or 240 operational days per year, €0.10/kWh charging, €0.40/kWh selling, full CAPEX, no subsidies, and no rental revenue), the business case for a power barge is not economically viable. Additional cost reductions, subsidies, or alternate revenue streams are required to make it feasible. Several levers can be changed in order to improve the business case, elaborated upon below. A combination of several levers is most likely warranted.


 
 

Members only

 

 
Membership
€199.00
Every month
€1,999.00
Every year

Premium tools and expert support at your fingertips

Shore Power Quickscan
Quick View

Don’t want to sign up? Check pay-per-use options

 

You might also like

Previous
Previous

Fuel and compliance costs for offshore workboat in North Sea

Next
Next

Choosing the right fuel: a brief guide to future prices and compliance costs